esc
Search documents
go
Browse entities
go
Corpus stats
go
About the data
go
AI settings
go
EFTA
Search
Search
Entities
About
Stats
Settings
⌘K
search
Search
Search syntax help
Dataset
Set 1
Set 2
Set 3
Set 4
Set 5
Set 6
Set 7
Set 8
Set 9
Set 10
Set 11
Set 12
Sort
Relevance
Most pages
Most words
Dataset
Newest
Oldest
Status
All
Extracted
Failed
DOJ Status
All
Removed
Available
Modified
Date Range
Undated only
–
Email Headers
Page Count
–
Saved Searches
+
57 results for “
"Complete Project"
”
Export
Keyboard Shortcuts
/
Focus search
Esc
Blur input
O
Open PDF
←
→
Paginate
Corpus: 1990-03-17 – 2025-12-01
←
October 2012
→
Mo
Tu
We
Th
Fr
Sa
Su
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Undated
(150,429)
None
Light
Medium
Heavy
EFTA02029505
Dataset 10
2012-10-05
3p
1,104w
…grass; trim all vines, acacia — owner's drive, blue beach, gym — work in progress - Peter to clean the sides of the road — work in progress - Bike Path - Black Heli Under Pads — not enough on site to
complete project
. Quote forwarded 10/5. Larry has provided another option - Review growth of sea grape - engineering area - Hydroseed all pull box areas & engineering - Take out the single tree in engineering - Peter might want to cut it, so not to damage lines 17. Roads…
https://www.justice.gov/epstein/files/DataSet%2010/EFTA02029505.pdf
EFTA02006082
Dataset 10
2012-10-02
3p
1,181w
…all vines, acacia — owner's drive, blue beach, gym — work in progress - Peter to clean the sides of the road — work in progress - Black Heli Under Pads — install at top of bike path at MC — not enough on site to
complete project
. Have located dealer, require amount to order will review 10/3 - Review growth of sea grape - engineering area - Hydroseed all pull box areas & engineering - Take out the single tree in engineering - Peter might want to cut it, so…
https://www.justice.gov/epstein/files/DataSet%2010/EFTA02006082.pdf
EFTA02316357
Dataset 11
2012-10-02
3p
1,182w
…all vines, acacia — owner's drive, blue beach, gym — work in progress - Peter to clean the sides of the road — work in progress - Black Heli Under Pads — install at top of bike path at MC — not enough on site to
complete project
. Have located dealer, require amount to order will review 10/3 - Review growth of sea grape - engineering area - Hydroseed all pull box areas & engineering - Take out the single tree in engineering - Peter might want to cut it, so…
https://www.justice.gov/epstein/files/DataSet%2011/EFTA02316357.pdf
EFTA00608664
Dataset 9
2013-11-22
22p
4,033w
…Landscaping To Be has been resolved Completed 6/1/13 — Reviewing with Aspen about plant location Spring 2014 7/18/13 — Have installed Lighting where planting is complete 7/27/13 — Before proceeding will review with JE on site 8/22/13 — Will
Complete Project
once Project 22 — Landscaping MH Complete 11/22/13 — Project will be completed Spring 2014 Page 5 EFTA00608669 Zorro Development Corp - Project Report 11/22/13 22B IN HOUSE - START END EST.COST NOTES LANDSCAPING …
https://www.justice.gov/epstein/files/DataSet%209/EFTA00608664.pdf
EFTA01124700
Dataset 9
2013-09-22
17p
3,057w
…Landscape Lighting Pending 5/1/13 — Unable to move forward until Project 22 — Landscaping Completion has been resolved Project 22 6/1/13 — Reviewing with Aspen about plant location 7/18/13 — Have installed Lighting where planting is complete 7/27/13 — Before proceeding will review with JE on site 8/22/13 — Will
Complete Project
once Project 22 — Landscaping MH Complete IN HOUSE - START END EST.COST NOTES PHOTO STATUS I 06/03/13 4/27/13 — JE Approved…
https://www.justice.gov/epstein/files/DataSet%209/EFTA01124700.pdf
EFTA00807586
Dataset 9
5p
738w
…Land acquisition terms Feasibility 14. Secure Offers from 3. Market study & Analysis Financial Study Operators Begin constructi 10. Begin negotiations with EPC 4. Pre-feasibility Financial contractors 15.
Complete Project
New Investors Study Engineering exercise Call Optl 11. Negotiate and Secure Offers from 5. Register BASE HoldCo Operators 16. Secure Senior Debt 6. Approach Senior Lenders 12. Obtain Construction & Operating Financing Licenses STRICTLY PRIVATE & CONFIDENTIAL EFTA00807587 Corporate & Financing structures New Investors own 100% of BASE HoldCo since beginning of construction…
https://www.justice.gov/epstein/files/DataSet%209/EFTA00807586.pdf
EFTA00522078
Dataset 9
2012-10-02
3p
1,183w
…all vines, acacia — owner's drive, blue beach, gym — work in progress - Peter to clean the sides of the road — work in progress - Black Heli Under Pads — install at top of bike path at MC — not enough on site to
complete project
. Have located dealer, require amount to order will review 10/3 - Review growth of sea grape - engineering area - Hydroseed all pull box areas & engineering - Take out the single tree in engineering - Peter might want to cut it, so…
https://www.justice.gov/epstein/files/DataSet%209/EFTA00522078.pdf
EFTA00811082
Dataset 9
2014-05-06
6p
1,267w
…58 4/5/19 - Balance to Airpro Complete Awaiting Final Invoice from RMC Electric Awaiting RMC Invoice 140 - START :END END EST.COST NOTES PHOTO STATUS PURCHASE/INSTALL X 6 UNIT HEATERS - GARAGES RC - 2/19/2019 $8,841.43 2/21/19 - 50% Deposit Paid to Airpro 3/29/19 - All Units Installed - Running 100% $8,841.42 4/5/19 - Balance to Airpro
Complete Project
Total 1[71.6_82.85 Complete Page 3 EFTA00811085 141 - Mitt I…
https://www.justice.gov/epstein/files/DataSet%209/EFTA00811082.pdf
EFTA01083718
Dataset 9
2012-05-08
5p
2,210w
…all cooling coils on all main air fans AC-1, AC-2 AC-3 AC_4 and all reheat zones to all rooms. RB to do cooling season start up PM. RB will
complete project
by May 25th. ■ Test emergency generator ATS switches EPP and emergency life safety system. RB to provide proposal for JEE approval for electrical engineering Test Company to assist in testing. We should run in emergency mode at least once per year. Scheduled for June…
https://www.justice.gov/epstein/files/DataSet%209/EFTA01083718.pdf
EFTA01177111
Dataset 9
2012-05-08
6p
2,252w
…all cooling coils on all main air fans AC-1, AC-2 AC-3 AC_4 and all reheat zones to all rooms. RB to do cooling season start up PM. RB will
complete project
by May 25th. Work Completed.5/17 ■ Test emergency generator ATS switches EPP and emergency life safety system. RB to provide proposal for JEE approval for electrical engineering Test Company to assist in testing. We should run in emergency mode at least once per…
https://www.justice.gov/epstein/files/DataSet%209/EFTA01177111.pdf
EFTA01177087
Dataset 9
2012-05-08
6p
2,252w
…all cooling coils on all main air fans AC-1, AC-2 AC-3 AC_4 and all reheat zones to all rooms. RB to do cooling season start up PM. RB will
complete project
by May 25th. Work Completed.5/17 ■ Test emergency generator ATS switches EPP and emergency life safety system. RB to provide proposal for JEE approval for electrical engineering Test Company to assist in testing. We should run in emergency mode at least once per…
https://www.justice.gov/epstein/files/DataSet%209/EFTA01177087.pdf
EFTA01205046
Dataset 9
22p
14,332w
REPORTER'S PRIVILEGE: 7TH CIR. The Reporters Committee for Freedom of the Press A chapter from our comprehensive compendium of information on the reporter's privilege —the right not to be compelled to testify or disclose sources and information in court — in each state andfederal circuit. The
complete project
can be viewed at www.rcfp.org/privilege Repor EFTA01205046 REPORTER'S PRIVILEGE COMPENDIUM TM CIR. Credits & Copyright This project was initially made possible by a generous grant from the Phillip…
https://www.justice.gov/epstein/files/DataSet%209/EFTA01205046.pdf
EFTA01850707
Dataset 10
2011-11-14
1p
299w
Subject:
updates
To:
'eevacation mail.com 'eevacation mail.com
…hanger on hold to LSJ projects complete -Internet at hanger completed. -Fax line has been run to telephone pole on street outside of hanger, waiting for LSJ personal to run wire into hanger for completion, once LSJ has available manpower to
complete project
. -Boeing 727 maintenance package is being review at Flight Star in Jacksonville, awaiting price quote, they have manpower to start project week of Nov 21st. -Midnight Express is due to arrive Tuesday (tomorrow) Nov.15th in St…
https://www.justice.gov/epstein/files/DataSet%2010/EFTA01850707.pdf
EFTA02036782
Dataset 10
2011-11-14
1p
299w
Subject:
updates
To:
jeevacationtfigmail.com[
[email protected]
];
…hanger on hold to LSJ projects complete -Internet at hanger completed. -Fax line has been run to telephone pole on street outside of hanger, waiting for LSJ personal to run wire into hanger for completion, once LSJ has available manpower to
complete project
. -Boeing 727 maintenance package is being review at Flight Star in Jacksonville, awaiting price quote, they have manpower to start project week of Nov 21st. -Midnight Express is due to arrive Tuesday (tomorrow) Nov.l5th in St…
https://www.justice.gov/epstein/files/DataSet%2010/EFTA02036782.pdf
EFTA02008660
Dataset 10
2011-12-14
1p
182w
Subject:
6727 add pricing
To:
[email protected]
[
[email protected]
];
…300 SAT/Internet 332k speed, $150,000 (best option for price since the KU band systems cost $700k. -Airshow with Four monitors $165,000 installed •AFIS data uplink to FMS's, TBD,. $100k guess -interior red room fabric change and seats and fwd table reinstalled in Boeing: $55,410.00 Banyan is fairly confident they could
complete project
for 500k however my gut tells me Eric's price will be $750k just my opinion thx tarry EFTA_R1_00509177 EFTA02008660
https://www.justice.gov/epstein/files/DataSet%2010/EFTA02008660.pdf
EFTA01739596
Dataset 10
2011-11-14
1p
299w
Subject:
updates
To:
'eevacation mail.com
…hanger on hold to LSJ projects complete -Internet at hanger completed. -Fax line has been run to telephone pole on street outside of hanger, waiting for LSJ personal to run wire into hanger for completion, once LSJ has available manpower to
complete project
. -Boeing 727 maintenance package is being review at Flight Star in Jacksonville, awaiting price quote, they have manpower to start project week of Nov 21st. -Midnight Express is due to arrive Tuesday (tomorrow) Nov.l5th in St…
https://www.justice.gov/epstein/files/DataSet%2010/EFTA01739596.pdf
EFTA02026837
Dataset 10
2012-10-01
3p
1,192w
…acacia — owner's drive, blue beach, gym — work in progress - Peter to clean the sides of the road — work in progress - Black Heli Under Pads — install at top of bike path at MC — not enough on site to
complete project
. Larry forwarding details - Review growth of sea grape - engineering area - Hydroseed all pull box areas & engineering - Continue to line all roads with stones - Take out the single tree in engineering - Peter might want to cut it, so not to damage…
https://www.justice.gov/epstein/files/DataSet%2010/EFTA02026837.pdf
EFTA02444150
Dataset 11
2009-05-22
1p
298w
Subject:
FW: irrigation estimates and system components
From:
Brice Gordon
To:
J Epstein[jeevacation©gmail.com]
…materials onsite in 16-21 days. I may have left out some items but I did check out your inventory so I have good idea of what is already onsite. I would be working with 1 or 2 of my employees to
complete project
. I can start immediately and I can work around current VI projects. As for landscape/ new designs/landscape maintenance/ideas I have all of that on disc and in binder, but I would like to see…
https://www.justice.gov/epstein/files/DataSet%2011/EFTA02444150.pdf
EFTA02315485
Dataset 11
2012-10-01
3p
1,183w
…acacia — owner's drive, blue beach, gym — work in progress - Peter to clean the sides of the road — work in progress - Black Heli Under Pads — install at top of bike path at MC — not enough on site to
complete project
. Larry forwarding details - Review growth of sea grape - engineering area - Hydroseed all pull box areas & engineering - Continue to line all roads with stones - Take out the single tree in engineering - Peter might want to cut it, so not to damage…
https://www.justice.gov/epstein/files/DataSet%2011/EFTA02315485.pdf
EFTA00686344
Dataset 9
2011-11-14
1p
297w
Subject:
updates
To:
[email protected]
…hanger on hold to LSJ projects complete -Internet at hanger completed. -Fax line has been run to telephone pole on street outside of hanger, waiting for LSJ personal to run wire into hanger for completion, once LSJ has available manpower to
complete project
. -Boeing 727 maintenance package is being review at Flight Star in Jacksonville, awaiting price quote, they have manpower to start project week of Nov 21st. -Midnight Express is due to arrive Tuesday (tomorrow) Nov.15th in St…
https://www.justice.gov/epstein/files/DataSet%209/EFTA00686344.pdf
1–20 of 57 results · page 1 of 3
«
←
1
2
3
→
»
Results by Dataset
57 total
Set 9
46
Set 10
8
Set 11
3