From: Emad Hanna
Sent: Friday, February 4, 2011 5:07 PM
To: Jeffrey Epstein
Cc: Rich Kahn
Subject: LSJ Mechanical Building Wire
Attachments: 02 -04-11-Abbott-Lineham -Req3.pdf
Jeffrey,
The attached wire request of $ 30,975.84 we will =lso hold until next week until you review the work done.
This is a contract for fuel piping in the amount of = 96,217, to date we have paid $ 55,860 and after the current request
is processed =here will be a balance due of $ 8,381.16