Rich,
Please see attached compiled list for next 7-8 weeks
Kyle
On Thu, Jan 3, 2019 at 4:34 PM Richard Kahn < > wrote:
can you please prepare one list summarizing projects to be finalized in the next 7-8 weeks for GSJ and LSJ
examples would be roofs on LSJ / GSJ RO
thank you
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue 4th Floor
New York, NY 10022
EFTA01009247