BERTHA
Repair Budget
August 27, 2007
SHIPYARD COSTS Unit Per Unit Labor Per Unit Material Per unit Sub Total Cost Notes
Haul / Launch Bertha 74 lit $15.00 $1,110.00 Hauled 8/10/07
Blocking. 74 Ift $3.00 $222.00
Transient Dock Fees 1 Day $124.12 $124.12
Lay Days 63 Days $122.10 $7,692.30
$9,148.42
MUST DO
Marine Survey 1 Tot $1,200.00 $1,200.00 Completed 8/24/07
Hydraulic installation 1 Tot $52,000.00 $52,000.00
$53,200.00
NECESSARY OUT-OF-WATER REPAIRS
Stuffing box replacement 2 Ea $445.00 $890.00 Applied
10 hrs $55.00 $550.00 Applied
Replace propellers 2 Ea $3,121.00 $6,242.00 Applied
3 hrs $55.00 $165.00 Applied
Clean the fuel system 1 Tot $500.00 $500.00 BH
12 hrs $37.50 $450.00 BH
Repair fuel leaks 1 Tot $1,200.00 $1,200.00 BH
12 hrs $37.50 $450.00 BH
Rework bilge pumping system 1 Tot $150.00 $150.00 BH
8 hrs $37.50 $300.00 BH
Repair/replace drum steering switch 1 Tot $400.00 $400.00 BH
3 hrs $37.50 $112.50 BH
Repair radar mount 1 Tot $800.00 $800.00 OH
$12,209.50
SHOULD DO
Purchase and install fenders 8 ea $800.00 $6,400.00
3 hrs $37.50 $112.50 BH
Purchase and install 1-1/4' dock lines 1 Tot $1,590.00 $1,590.00
2 hrs $37.50 $75.00 BH
Repair oil leaks 1 Tot $500.00 $500.00
40 hrs $37.50 $1,500.00 BH
Repair exhaust leaks 1 Tot $1,200.00 $1,200.00
Page 1 of 2
EFTA00616406
BERTHA
Repair Budget
August 27, 2007
32 hrs $37.50 $1,200.00 BH
Augment battery banks 4 Tot $310.00 $1,240.00
8 hrs $37.50 $300.00 BH
$14,117.50
WISH LIST
Clean and paint 8 gals $95.00 $760.00
36 hrs $37.50 $1,350.00 BH
Rework / enclose bridge 1 Tot $0.00 more info to follow
hrs $37.50 $0.00 BH
Install engine start/stop controls 1 Tot $325.00 $325.00
8 hrs $37.50 $300.00 BH
Tune engines 1 Tot $125.00 $125.00
8 hrs $37.50 $300.00 BH
Install permanent windows and hatches 1 Tot $0.00 more info to follow
hrs $37.50 $0.00 BH
Rework engine compartment lighting 1 Tot $1,054.00 $1,054.00
8 hrs $37.50 $300.00 BH
$4,514.00
Total $94089.42
evaaeA-,1/O
7O7
Page 2 of 2
EFTA00616407
AI Analysis
Summarize this document or ask questions about its contents using Claude.
Typical cost: less than $0.01 per query with Haiku. Model can be changed in Settings.
Add API Key in SettingsI
BERTHA
Repair Budget
August 27, 2007
SHIPYARD COSTS Unit Per Unit Labor Per Unit Material Per unit Sub Total Cost Notes
Haul / Launch Bertha 74 lit $15.00 $1,110.00 Hauled 8/10/07
Blocking. 74 Ift $3.00 $222.00
Transient Dock Fees 1 Day $124.12 $124.12
Lay Days 63 Days $122.10 $7,692.30
$9,148.42
MUST DO
Marine Survey 1 Tot $1,200.00 $1,200.00 Completed 8/24/07
Hydraulic installation 1 Tot $52,000.00 $52,000.00
$53,200.00
NECESSARY OUT-OF-WATER REPAIRS
Stuffing box replacement 2 Ea $445.00 $890.00 Applied
10 hrs $55.00 $550.00 Applied
Replace propellers 2 Ea $3,121.00 $6,242.00 Applied
3 hrs $55.00 $165.00 Applied
Clean the fuel system 1 Tot $500.00 $500.00 BH
12 hrs $37.50 $450.00 BH
Repair fuel leaks 1 Tot $1,200.00 $1,200.00 BH
12 hrs $37.50 $450.00 BH
Rework bilge pumping system 1 Tot $150.00 $150.00 BH
8 hrs $37.50 $300.00 BH
Repair/replace drum steering switch 1 Tot $400.00 $400.00 BH
3 hrs $37.50 $112.50 BH
Repair radar mount 1 Tot $800.00 $800.00 OH
$12,209.50
SHOULD DO
Purchase and install fenders 8 ea $800.00 $6,400.00
3 hrs $37.50 $112.50 BH
Purchase and install 1-1/4' dock lines 1 Tot $1,590.00 $1,590.00
2 hrs $37.50 $75.00 BH
Repair oil leaks 1 Tot $500.00 $500.00
40 hrs $37.50 $1,500.00 BH
Repair exhaust leaks 1 Tot $1,200.00 $1,200.00
Page 1 of 2
EFTA00616406
BERTHA
Repair Budget
August 27, 2007
32 hrs $37.50 $1,200.00 BH
Augment battery banks 4 Tot $310.00 $1,240.00
8 hrs $37.50 $300.00 BH
$14,117.50
WISH LIST
Clean and paint 8 gals $95.00 $760.00
36 hrs $37.50 $1,350.00 BH
Rework / enclose bridge 1 Tot $0.00 more info to follow
hrs $37.50 $0.00 BH
Install engine start/stop controls 1 Tot $325.00 $325.00
8 hrs $37.50 $300.00 BH
Tune engines 1 Tot $125.00 $125.00
8 hrs $37.50 $300.00 BH
Install permanent windows and hatches 1 Tot $0.00 more info to follow
hrs $37.50 $0.00 BH
Rework engine compartment lighting 1 Tot $1,054.00 $1,054.00
8 hrs $37.50 $300.00 BH
$4,514.00
Total $94089.42